User Guide
Why can I only view 3 results?
You can also view all results when you are connected from the network of member institutions only. For non-member institutions, we are opening a 1-month free trial version if institution officials apply.
So many results that aren't mine?
References in many bibliographies are sometimes referred to as "Surname, I", so the citations of academics whose Surname and initials are the same may occasionally interfere. This problem is often the case with citation indexes all over the world.
How can I see only citations to my article?
After searching the name of your article, you can see the references to the article you selected as soon as you click on the details section.
 Views 19
 Downloands 3
DEMOKRAT PARTİ DÖNEMİ (1950-1960) ERZURUM KAMU YATIRIMLARINA BİR ÖRNEK: TORTUM HİDROELEKTRİK SANTRALİ
2021
Journal:  
ANASAY
Author:  
Abstract:

Yapımına 1952 yılında başlanan ve Mayıs 1960’da hizmete giren Tortum Hidroelektrik Santrali, Erzurumluların çok uzun zamandan beri hayata geçmesini bekledikleri bir projeydi. Bu uzun bekleyişe rağmen projenin ihalesinin ardından yapım ve hizmete girme aşaması da planlanandan uzun sürmüş ve yoğun gayretler sonucu gerçekleşebilmişti. Bu makalede 1960 yılına kadar geçen sürede Erzurum’un elektrik sorunu ve bu sorunun giderilmesine yönelik çalışmalar ile Erzurum’un elektrik meselesine kesin çözüm olarak gösterilen Tortum Hidroelektrik Santrali’nin yapım ve hizmete giriş süreci ele alınmıştır. 1951 yılında Bakanlar Kurulu onayından sonra, inşaat ile makine ve teçhizat ihaleleri yapılan Santralin 1956 yılı itibariyle bitirilmesi planlanmış ise de yaşanan aksaklıklardan dolayı ancak 1960 yılında tamamlanabilmiştir. Santralden 1960 Mayıs ayı itibariyle de elektrik üretimine geçilerek şehre elektrik verilmeye başlanmıştır. 1972 yılına kadar Erzurum Belediyesinin işletmesinde kalan santral, aynı yıl içerisinde Enerji ve Tabi Kaynaklar Bakanlığına bağlı olan TEK’e devredilmiştir.

Keywords:

The Democratic Party (1950-1960) An example of the ERZURUM public investments: TORTUM Hydroelectric Plant
2021
Journal:  
ANASAY
Author:  
Abstract:

The Tortum Hydroelectric Power Plant, which began its construction in 1952 and entered service in May 1960, was a project that the Erzurumlists have long been expecting to implement. Despite this long waiting after the project’s offer, the construction and service stage was also longer than planned and could be achieved as a result of intense efforts. This article discussed the construction and service process of the Tortum Hydroelectric Power Plant, which has been shown as a precise solution to the electricity issue of Erzurum during the period until the 1960s and the work on the resolution of the electricity problem of Erzurum. After the approval of the Council of Ministers in 1951, the plant was planned to be completed in 1956 for construction and machinery and equipment, but due to the faults it was only possible to be completed in 1960. In May 1960, the power plant began to produce electricity in the city. Until 1972, the plant remaining in the operation of the Erzurum Municipality, was transferred to the TEK, which was affiliated with the Ministry of Energy and Natural Resources in the same year.

Keywords:

0
2021
Journal:  
ANASAY
Author:  
Citation Owners
Information: There is no ciation to this publication.
Similar Articles












ANASAY

Field :   Sosyal, Beşeri ve İdari Bilimler

Journal Type :   Ulusal

Metrics
Article : 291
Cite : 401
2023 Impact : 0.176
ANASAY